We managed to set a record today, for the greatest number of sleepers we’ve moved by train in 1 day! A total of 1,337 sleepers have been dropped out trackside, with a further 450 loaded and ready to go in the morning.
![](https://vgrcivil.blog/wp-content/uploads/2023/11/received_287560167042005.jpeg?w=1024)
![](https://vgrcivil.blog/wp-content/uploads/2023/11/received_1447474055836041.jpeg?w=768)
First off we unloaded a full train load of fast clip sleepers out by Pipeline Crossing, these will be used in the straight and very large curve nearby.
![](https://vgrcivil.blog/wp-content/uploads/2023/11/received_760323819254352.jpeg?w=1024)
![](https://vgrcivil.blog/wp-content/uploads/2023/11/received_285948714438499.jpeg?w=1024)
![](https://vgrcivil.blog/wp-content/uploads/2023/11/received_1107886040376371.jpeg?w=1024)
Then off to Muckleford for a full reload, this time e clip type sleepers, for use in the curves on the Down side of pipeline crossing.
![](https://vgrcivil.blog/wp-content/uploads/2023/11/received_1198655471537891.jpeg?w=768)
They were dropped out well ahead of lunch, in time to return to Maldon and unload the next semi load of sleepers arriving.
![](https://vgrcivil.blog/wp-content/uploads/2023/11/received_282594088087177.jpeg?w=1024)
![](https://vgrcivil.blog/wp-content/uploads/2023/11/received_349274921042064.jpeg?w=1024)
Cross loaded from the truck straight onto the train, nice to not have any double handling.
Once they were loaded, all remaining fastclip sleepers at Maldon were loaded, happening by fluke to perfectly match the number needed to make a full train load!
![](https://vgrcivil.blog/wp-content/uploads/2023/11/received_266215159757936.jpeg?w=1024)
Another discharge well on the Down side of Pipeline crossing further around the sweeping curve saw the wagons emptied again, ready for the final load of the day at Muckleford.
Tomorrow we’ll be meeting at Maldon at 8am, we do need to fuel up the digger and do a couple of small odd jobs, before we head out to drop out the loaded sleepers. However by the end of tomorrow, we should have another few hundred sleepers dropped out, all helping to work towards getting them into the track.