Finishing off

It was quite a simple day today, with no staggering achievements but we did get the last of the timber sleepers from curve 8 bundled and all of those from the curve loaded onto a wagon and dropped at Muckleford.

We also had time to tidy up the ballast at yesterday’s worksites which leaves both looking pretty swish.

Next week’s attentions will be at Castlemaine Yard, tidying up our materials in preparation for the new engine shed project.

Curve 8 and more

The rest of curve 8 received the 1 in 3 concrete sleeper treatment today. This leaves only one long curve (11) on the whole railway which hasn’t been either re-railed or re-inforced with concrete sleepers.

Nothing too exciting, no new methods or techniques, however we are certainly perfecting our ways as all 42 were installed and clipped up before lunch.

We’ve decided the shovel measure works, so we’ll run with that from now (maybe a slightly reinforced version as some panel beating was required!).

We managed to squeeze in enough preparation on Tuesday to actually insert 10 sleepers and tamp them up, to keep the gang busy first off today. The Tuesday preparation is the make or break of a successful Thursday/Friday.

Our success was so great we even completed the same treatment between curves 9 and 10 where only 18 sleepers were needed. Unfortunately Tuesday’s preparation didn’t extend to here so this was a little more time consuming (the sleepers were still stacked and the screws not removed).

We even completed all the tamping at both locations, done under Rolf’s watchful eye. Tomorrow afternoon will see some ballast scraping to tidy up and if we get time we’ll bundle the sleepers too.

Tomorrow morning will be in Castlemaine Yard tending to various bits and pieces.

Curve 8

Yesterday saw the completion of the 82 (not 78 as we thought Thursday) concrete sleepers in curve 8.

The final biscuits and clips were in in no time.

Then onto the brilliantly dusty job of ballast spreading.

The whole length received a tamp with Rolf sighting any dips and twists. It is probably one of best looking sections we’ve done so far and we’re pretty happy with it.

We also made use of our gang to bundle all the reusable sleepers from this curve as well as from curve 10.

Next week will be more of the same, which will see this curve finished and onto the next.

Curve 8

Another busy day concrete sleepering.

Unfortunately not all our plans came off, with our regular assistants from Middleton Prison having to call in sick at the 11th hour.

We did however still achieve an enormous amount. We had hoped to finish the whole curve this week but it’ll only take a day to complete it next week now.

As the screws had been removed on Tuesday, only this one damaged screw required attention. Sleepers were also distributed and pads installed on Tuesday.

We tried a couple of small differences today, the first being our new shovel measurer… A simple bit of 50mm RHS welded on the end of one of our broken shovels, bent to this shape. It removes the need for the wooden blocks. It actually worked really well and certainly sped things up.

While the lifting was happening, all jewellery was distributed as well as the old collected and removed.

Morning tea shows the gang well and truly enjoying a relax. It wasn’t overly hot but the humidity was high.

Another alteration was using the digger to hold up the sleepers while the first inner biscuit was installed and clipped. This saved a lot of manpower, probably not quicker but it was better use of our workforce.

This was followed up by the gauger and small crew installing the other inner biscuit and clip.

We didn’t install any of the outer biscuits until much later which certainly sped up proceedings.

By 2pm we’d inserted and started the clipping of all 78 that we’d set out to do so we started installing the outer biscuits and clips and achieved around 20 before we knocked off.

The last clip of the day going on, a nice feeling knowing we’d achieved so much and still had tomorrow to finish off.

We’ll be back tomorrow finishing off the clipping then sorting the removed sleepers and bundling the reusable one. Meet Maldon 8am or site from 8.30am.