Curve 9

We’re now officially half way through Curve 9, with the high leg completed today, 5 lengths of rail, totalling 214m.

We actually finished that quite early in the day, so we’ve removed all the screws from the low leg and prepared the rails to go in.

Hopefully on Thursday, weather permitting, we’ll get most of the low leg completed. Meeting at Maldon 7.45am or on site from 8.15am on Thursday.

Curve 9

Despite the rain, we managed to install another 163m of rail today, into the high leg of Curve 9.

The difference in this section, with nothing more than the new rail is quite noticeable.

We’ve also distributed the jewellery right through the curve to speed things up next week.

Today’s effort takes us to just under half way around the high leg of the curve, meaning we should be able to get the whole curve completed next week.

This week’s rerailing total came to 617m, with the monthly total so far sitting at 1192m.

Tuesday’s gang will meet at Maldon at 8am or out on site from 8.30am.

Curve 10

On a day that felt like it was going to be a washout, we achieved managed to achieve an enormous amount.

We began with the goal of installing 3 lengths of rail into the low leg of the curve, as the weather was looking very unfavourable.

However after a few extended breaks sheltering in the vehicles, we ended up installing 10 lengths, a distance of 374m, taking up almost up to the start of Curve 9.

It’s a little hard to tell from this pic, but the end point was another rail length past where the digger is.

And it wouldn’t be a day in the rain without a little bit of bogging.

Unfortunately simple and convenient to extract, taking all the fun out of it, we didn’t even have to get the digger off the track.

Tomorrow’s gang will meet on site from 8.15am (mind you don’t park in any soft ground), the weather is looking a bit interesting, so it may end up being more preparation for the next rerailing than actual rerailing, allowing us to hid in vehicles to escape the rain if required.

Rerailing

A further 80m of rail installed today, completing the high leg of curve 10.

The afternoon was spent removing the screws from the low leg, dropping out all the jewellery required and preparing the joints. We’ve also removed all the anchors from the next curve. Hopefully all that saves us a lot of time on Thursday and we can make some significant headway in knocking over Curve 10 and starting Curve 9.

We’ve also set a new yearly record for rerailing, 4289m so far this year. Our other high ranking year was 2018, where we rerailed 4160m. The long rails and concrete sleepers have certainly sped up the rerailing process, with less than half the physical work required.

Thursday’s gang will be meeting on site from 8.15am or at Maldon at 7.45am.