More concretes

Another 59 concrete sleepers installed today, along with a tamp and ballast scrape it’s looking very snazzy.

After the last sleeper was in, the ballast was scraped up ready for tamping.

It all went very well until the tamper blew a hose. But not to worry, the hydraulic supplies in Castlemaine sorted us out nice and quickly with a new one.

The job looks quite impressive.

Despite all this the gang also removed the dog spikes past sawmill road ready for next week, only the screws to go now.

Next week will be back here, aiming at around a similar number or possibly a few more weather depending.

Concrete Sleepers

Despite the heat and wind the gang achieved an extremely impressive 85 concrete sleepers installed into tangent 8-9.

It was done in the usual fashion, however testing out our new grabs!

They worked very well and it is likely they will speed up the operation greatly.

We still made use of the scarifier to speed things up even more so.

John, Clive and Mal hard at work clipping up.

We found in this section that pushing out the gauge was not required, which made the job a bit easier.

We gave up just after lunch once the wind came up and bush fire risk became too great (thankfully nothing we do during this particular job could cause a fire, but we carry large volumes of water and fire extinguishers just in case).

Another great effort from our hard working gang.

We’ll be back into it tomorrow, with another 80 odd ready to go in, this time in much more plesant weather.

Meeting Maldon 8am or site from 8.30.

Ballasting

A very long and hard day’s work, but we’ve got the turntable track back up and running.

Job one was tie up the last of the loose sleepers.

It took most of the morning but the old ballast was collected up and transferred over to the new track.

With some rock on, it was starting to look more impressive.

Even the point lever has been installed and it works!

A lot of lifting was required to achieve a smooth surface, still more lifting is needed, but that will require more ballast. As this is only a loco road, it’ll be quite adequate for years just like this.

The end result and a very exhausted gang proud of their efforts.

New turnout

Well today was the day. The new turnout went in.

First up was pulling up the old track and scraping away ballast ready for the move.

A lot of fine movements and measuring were required to locate the turnout and the approach roads exactly.

The turnout has even been clipped to the correct location, as it will be some time before the straight leg comes into use. It looks very smart.

With the trusty truck being the first beast over the new turnout.

After getting the turnout exactly right, we moved our attention to slewing the existing track.

It took quite a bit of running back and forward to achieve the amount of movement required.

Part way through the track looked terrible! Thankfully it’s all very flexible.

The track has actually been slewed completely off it’s old road bed onto the prepared ground.

With a nice set of reverse curves installed to allow access onto the turntable.

The job’s not finished yet, with the final rails still to be bolted up, ballast to be applied and lots and lots of lifting and tamping to do, we’ll be busy tomorrow, any extra hands very welcome.

This marks a big step forward in the Castlemaine project as it now allows all trenching to be finished and shed construction is now unimpeded by obstacles.

This weeks Civil Saturday will again be at Castlemaine, meeting A box from 8.30am.