A successful day today, the first without any real rainfall in quite a few dayswhich certainly improved moral.
We’ve completed the trackwork part of 3 siding, just a light ballast and tamp to go.



Then we headed down to make a good solid start on the 2nd turntable track. We’ve got about 1.5 rail lengths clipped. The rooster decided he needed to inspect the progress and then annoyed us right through afternoon tea!
Thursday will see us grout in the pit timbers we prepared on Friday, then we’ll get into doing some more work on this siding. However, given parking may be problematic this week, we’ve going to suggest parking is down at the station, with a gentle stroll up to the depot area. Meeting at the depot area around 8.15 on Thursday.