Rail Recovery

A small gang of 4 today, but given all the preparations done by the past few gangs, we have just about set a record for the amount of track sledded in one day.

Approximately 700m of rail has been sledded and dragged up towards the junction.

Getting us to just short of the Lawrence St. Bridge. This is a very big step towards the end of the project, with only about 300m of rail still to be sledded.

Tomorrow we’ll be back here, hopefully sledding another 100m before we run into all the stockpiled rail. We’ll then turn our attention to collecting all the jewellery and getting rails ready for cutting on Thursday. (well do the final sledding then).

Meeting Maldon Junction from 8.15am.