Rail Recovery

Another successful day, all the loose rail near the junction was broken into it’s lengths and stacked beside our track ready for carting away.

We have even sledded and dragged up to the junction another 300m of rail, from Moscript St.

We are hoping to sled on Monday and Tuesday next week, which should hopefully see the rail lifting part of the job done. With a bit of luck by the end of the next fortnight, we’ll have most of the jewellery stockpiled and a good number of the sleepers out of the roadbed too.

There’s still a chance we might be all done be Xmas, so if you’re feeling like an extra day on the gang sounds alright, you’d be more than welcome.

Meeting between Moscript St and the Junction from 8am on Monday.