Some fine tuning

Yesterday was spent adjusting, tweaking and improving the track over Muckleford Creek Bridge.

The Down end had the dips removed by jacking and tamping, while the up end received much more attention.

3 panels of track were re-aligned to turn a series of flats and kinks into a stunning curve off the bridge (as it’s meant to be). We even replaced 2 joint sleepers that weren’t doing a great job with Concrete, just off the bridge.

Unfortunately we forgot to grab a before picture, but the result is a complete transformation.

Next week will be a rest from Bridge work while we complete some more re-railing near Bendigo Road and install more concretes into curve 10.