Thursday Workday

Given the latest forecast is still saying Rain, Thunder and Wind for Thursday, we’ve made the decision to cancel the workday tomorrow. Check back for details of Friday, it’s looking a little better, however we’ll put out a post on the blog tomorrow night confirming the details.

Unfortunately, this year’s weather has been a little unkind to our civil activities, however it’s nice to see it so wet and green.

At stage next Thursday is not looking much better, hopefully that’ll change, however if anyone is interested in moving their day to Tuesday next week, we can easily accommodate many extra hands as we insert sleeper plates, drill holes and stand spikes.

Sleeper plates

Another action filled day of dropping out and stacking sleeper plates! We certainly feel we’re getting close to earning our proficiency badges now.

A small team also managed to get all the standing spikes driven, meaning we’ve now got only one side to go! Sounds easy if you say it fast.

The afternoon was spent doing the glorious task of stacking sleeper plates onto pallets! We managed 4 pallets worth before all of us decided we’d achieved quite a sufficient amount! That’s around 960 plates, which sounds a lot, until you’re out on the ground and realise just how much distance we’ve covered with the rerailing, no doubt we’ll still need to load up at least another 3 pallets before the job is done.

Thursday and Friday are looking wet, particularly Thursday. Check back here Tomorrow night for details of Thursday, however it’s looking like it’ll be wet.

Drilling and Standing Spikes

Today was a whole day dedicated to drilling holes and standing dog spikes. We’ve now drilled a hole in one side of everytimber sleeper between Muckleford and Sawmill Rd, with just the whole other side to go now!

Tuesday’s gang, which will meet at Maldon 8am or out near Curve 10 from 8.30am, will drive the spikes stood today and begin dropping out plates for the other leg.

Sleeper Plates

A successful day of inserting sleeper plates, with one leg now all under and tamped.

We even found plenty of time to start drilling and standing spikes, with several hundred metres of that completed.

And we had enough people on hand to drive a couple of hundred metres of spikes also.

Today saw one of our new toys tested. A trolley for the Excavators. We’re still working through developing the operating procedure and although we think we’ve covered all bases, a field test is always required to make sure everything behaves as expected, it certainly seems to and has already improved productivity greatly! No doubt this and it’s slightly bigger cousin will feature regularly on here!

Tomorrow’s crew will continue with the drilling and spiking, starting from Curve 9 (the curve on the Down side of Sawmill Rd Crossing) from 8.30am.