Unfortunately today ended up being a bit of a wasted day… the rain just got heavy and more constant as the day progressed!
A few spikes did get driven, until the spiker broke (nothing major but it does need that bit to work, that parts now on order, but we’ll switch back to the other spikes tomorrow to get it happening)
A few more spikes were started, however the rain did put pay to that too. But at least the boys found another turtle, it’s that time of year when they’re out and about, we’ve seen quite a few of late.
So after a long morning tea, a call was made to the mechanical department to see if they had any indoor jobs for us and by sheer fluke, they needed some extra hands to assemble some pallet racking.


This is inside the new workshop at Castlemaine. After a bit of head scratching, we quickly worked out how they go together.


The workshop comes with its own scissor lift, which turned out very useful in assembling the racking.

We managed to string this job out into several hours of work, mainly to avoid having to go back out into the rain… Once completed however, we did call it a day.
Tomorrow, as the weather is potentially a little iffy, we will meet at Maldon at 8am, where we’ll plan our day according to the weather, there is a few options so we should be right to achieve something.