Well we’re into clean up mode at the moment. All the fastenings between Donkey Gully Rd and Hutchinson’s Ln Bridge have now been stockpiled.
Tomorrow’s gang will be working on the section between Yapeen Rd and Hutchinson’s Ln Bridge, meeting midway between the two from 8.15am.