Point timbers

Today saw us install a further 10 point into Maldon yard.

The three turnouts just past the down end of the platform were the recipients and quite rightly so seeing they see the most use.

With the mess all tidied up the job looks quite nice, it should mean we don’t need to do any emergency repairs in the yard any time soon (allowing us to keep focusing on other things).

We also replaced and tightened a few fishplates in the loco road, which were getting quite bad.

Next week we’ll be loading and shipping material off to Castlemaine ready to start work laying track in the carriage shed extension. Tuesday will be an odds jobs day at Maldon loading and sorting materials. Meeting 8am