Today saw us with a total of 170 sleepers installed this week, all their jewellery dropped out, ready for clipping up tomorrow.
Installing a few sleepers was really a side line to today’s work. The main task was removing the fastenings for the remainder of Tangent 8-9, about 200 sleepers were unfastened, all the jewellery collected.
We even managed to do the 50mm lift for the full length, ready for sleeper changes next week.
We’ll be out on site again tomorrow, from around 8.45am clipping up the 170 sleepers already inserted.