Concrete Sleepers

As promised, it was a day of loading concrete sleepers. 388 in total were loaded onto all our suitable wagons, including the latest addition to the fleet QB2 currently on loan to us from Steamrail.

This number allows us to complete tangent 8-9 with about 40 left over for the next tangent.

Next week will include dropping these out and hopefully starting to get them under the track.