Sleepers

A bit more sleepering today, with around 60 installed into curve 16.

We’re starting to get pretty slick with these timber sleeper changes and will shortly need to go and install some more concrete sleepers to release enough timber for the rest of the length towards Maldon.

We’ll be out again tomorrow, with a plan being to tamp all these up, box up everything from the past few weeks. Meeting Maldon 8am or curve 16 from 8.15am.