It was a big day of rail towing today, with around 20 rails now up to the next crossing.
The gang kept themselves busy re-installing some temporary rails into this very quiet dirt track as that will be by far the easiest way to continue the dragging and the least disruption for all involved.
Job done and tested with a few cars, very snazzy. We’ve got one more dirt track to do in the same way tomorrow, which will allow us to do an enormous amout more rail towing, and of course recovery.
We’ll be back on site tomorrow, meeting at Goudges Ln around 8.15am – 8.30am.