Well today saw trench back filling and the completion of the new turnout in Castlemaine.
Plenty more trench filling required once all the services are in, which will be over the next few weeks.
The new turnout is planned to go in in a fortnight, once the site is levelled and cleared ready for track slewing.
Next week will be the final tweaking of the track over Muckleford Creek Bridge.
We’ll tend to these very minor discrepancies and correct the slight under gauge issue (that’s been there for 30 years!)