Concrete Sleepers

Today was all about distributing the concrete sleepers that we’d dropped out lineside previously.

Every sleeper required checking for pad condition and installation if missing, before being placed at suitable intervals along the running line.

With a follow along run to drop them out lineside next to their new home.

It looks very impressive with all 272 dropped out awaiting insertion. We require only 11 more to complete this straight (Bridge Excluded).

The next straight towards Castlemaine was also marked up in the 1 in 3 pattern ready for fastening removal and re-sleepering, with only 223 required there.