Another good day on the track, with 176 concrete sleepers dropped out in various places for the next few jobs.

The afternoon was spent preparing more 80lb rail.

34 lengths were prepared and loaded onto a wagon. These will be for the UP leg near Bendigo Road.

Next week will be another big one, with our aim being to install at least 100 of the 124 concretes needed in curve 8. It’s success is largely due to any preparation we can do on Tuesday, so any extra hands Tuesday would be very greatly appreciated.