Castlemaine Re-sleepering

Hot! That’s the only way to describe today. Unfortunately we’ve only got worse coming…

Around 170 sleepers were unfastened today, with about 30 of those now replaced, around 50 more scarified and still around 50 to be removed with the rest just needing scarifying, not at all a bad days effort.

We’ve got help from some of volunteers of the Pichi Richi Railway, which has been a massive boost, as they’re more used to this heat than us.

Work will kick off at 7 tomorrow morning from the big red shed if anyone’s available and we understand if only half a day suits given the weather.

One thought on “Castlemaine Re-sleepering

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s