Rail Recovery

We seem to be powering ahead with Rail Recovery.

We’ve now lifted and dragged all the rails on the Guildford side of Goudges Ln to between Donkey Gully Rd and Grudges Ln, it’s a lot of rail we’ve crammed into the 800ish metres, but Donkey Gully Rd marks half way, so we’re feeling pretty pleased.

We’ve begun the dreaded task of cleaning up the jewellery and sleepers… It’s not a fun or fast job but we’ll get there. Tomorrow we’ll be meeting at Goudges Ln from 8.15am.

Rail Recovery

We seem to be powering ahead with Rail Recovery.

We’ve now lifted and dragged all the rails on the Guildford side of Goudges Ln to between Donkey Gully Rd and Grudges Ln, it’s a lot of rail we’ve crammed into the 800ish metres, but Donkey Gully Rd marks half way, so we’re feeling pretty pleased.

We’ve begun the dreaded task of cleaning up the jewellery and sleepers… It’s not a fun or fast job but we’ll get there. Tomorrow we’ll be meeting at Goudges Ln from 8.15am.

Rail Recovery

Well after all the work recently undertaken at Castlemaine, we’ve been let out for good behaviour so we’re back into rail recovery.

A few rails have been moved today, with tomorrow being the first official day of works resuming.

Tomorrow, we’ll meet Maldon at 8am, then from 8.30am near Godrey’s Ln Yapeen.

We did it

Today was very successful, it was pretty full on and long but we’ve got plenty to show for it.

We began by hanging the last doors on the loco shed, and for some reason we brought all of our toys up along the new track to the shed, just because we could.

All the doors are now hung, a big step in the project. This shot also shows just how nicely the track has come up.

And as promised… A headlight from within the shed.

We did it! It’s not the biggest project we’ve undertaken, but has certainly taken a lot of effort and has all been crammed into a very short space of time. Congratulations to everyone who has helped us along the way.

The centre door is almost fully complete. Its fancy top latches and bottom bolts have been installed, at this stage we’ve just install temporary tubing into the ground to take the bolts as it’s likely all that will end up as concrete in the near future.

The latches and bolts work perfectly and should prove much less hassle than the latches on the carriage shed doors.

And the rail bollards for these doors have been installed also, just some catch chains need fitting for keeping them open.

The day also involved loading all the stacked rail and palletised fastenings onto the wagons, so the whole site is looking very tidy and it’s beginning to look like a usable depot.

Anther extremely successful week and hopefully plenty more of those to come as from Monday, we’re back into Rail Recovery.