Its been a while since the last blog but we are progressing well, last week’s total saw us reach 240 and this week we’ll only have installed 60, however we’ve got some other tasks to attend to over the next week, however there is only about 388 sleepers left to reach Muckleford Creek Bridge now.


Although all of what were going to put under this week is already done, we’ve still got 80 that need clipping up tomorrow, so that’ll keep us busy for a while. Meeting at Maldon 8am or out on site from 8.30am