Concrete Sleepers

Well we’re back into it! Resleepering with 100% concrete. We’re starting at Donkey Farm Track and heading towards Muckleford Creek Bridge, replacing the last 1350 timber sleepers remaining between Maldon and Muckleford.

Being a short week and settling back into the swing of things, we’ll most probably only get 130 under this week, however that’s a good solid start, taking us right up to the start of the curve.

There is still plenty for tomorrow’s crew to do, lots of clipping up and tidying up. Meeting Maldon 8am or out at Donkey Farm Track from 8.30am