Tidy up and Bridge Work

Today saw us tidy up around Castlemaine and tamp most of the recent work.

We’ve got a few point timbers yet to squeeze up, which will be Monday’s task, before we take the excavator through to Muckleford for Bridge Work.

This afternoon saw the start of our 2023 Bridge program, with the relevant bolts associated with the first planned works loosened and prepared for removal next week.

Tomorrow’s gang will continue with this task from Muckleford Creek Bridge from 8.30am tomorrow.