Well we’ve made excellent progress today, with all the available track (as in where no rails are stacked in between) sledded up towards Fryers Rd – .

We’ve got less than 400m to go to Fryers Rd now, but it’ll be a little while before we complete that, as a big rail shuffle up ahead is required.

Tomorrow we’ll get Moscript Street ready for dragging across on Thursday. Meeting at Moscript Street from around 8.30am tomorrow and 8.15am on Thursday.