Rail Recovery and Snazzy Truck

Well, it was a long day, but an extremely successful one. We’ve now sledded approx. 2/3 of the length between Goudges Ln and Donkey Gully Rd and dragged all the loose rail up to Donkey Gully Rd ready for transfer on Monday next week.

Early next week should see us with all the rail lifted to Donkey Gully and dragged down to Fryers Rd.


In completely unrelated news, the large crane truck has received a bit of a touch up to it’s paint job. It looks like a new truck! Amazing what a bit of fresh paint can do.

We’re all over the place tomorrow, tending to a few odds and sods required back on our own Railway, so no real workday is planned.