Another big day at Castlemaine. The water meter and fire service/ booster point are now installed.
The power is getting closer also, with most of the conduit now in place and all their trenches dug.
There’s a bit to go yet, but Wednesday next week the site should look much more normal.
Due some boundary complications, the power actually runs through next door’s property, The Mill, who we’re very thankful for their fantastic cooperation.
We’ve even back filled the first section to satisfy the ending of a permit for works near some live optic fibres.
There will be a little more work here in the morning, but more so Monday / Tuesday will see lots of the trenche filled.
The gang will be out tomorrow at Muckleford Creek Bridge lining and lifting the track. Meet Maldon 8am or sit’s from 8.30am