Recap of recent works

There has been a lot happen of the past few weeks and unfortunately not all of it has made the blog, so here is a quick recap of what we missed sharing.

V/Line shutdown works:

We made the news!

The video largely speaks for itself, however it really has been a major turning point for our railway, being able to use Concrete Sleepers instead of relying on 2nd hand timber, every sleeper we put it now should comfortably last 40+ years (probably much much longer) compared to the enormous task of replacing every timber sleeper every 20-25 years!

Following the V/Line shutdown works, where we managed a staggering 252 concrete sleeper insertions, 29 point timbers and lots of incidental jobs, we had a very impressive climax to the week with a visit from a production tamper.

img20200703145120

V/Line required the use of a tamper to complete their portion of the works, however they had hired the machine for a full day and intended to get a whole day’s use out of it.

img20200703152008

The turnout featured in this photo was the main task that the tamper had been brought in for (our connection to V/Line), given it required a slight lift, our adjoining turnout also required a comparable lift to bring it to the new level, so the tamper was always going to need access to our track.

img20200703141752

However given the John Hollands Crew managed to complete the required turnout tamping and lifting in good time, they had sufficient time to complete some additional tamping for us.

The entire section worked on during the shutdown (approx 500m) received a production tamp, lift and line in an afternoon, leaving the track in a very high standard (see pics below) – easily 2 weeks work if we were to try and achieve a vaguely similar standard

We are extremely grateful to V/Line for their incredible support during the recent works, they have been very supportive and understanding of our situation and helped us where ever they could, we hope they found us equally supportive and helpful (in the small ways that we could be).

We are also very grateful to John Hollands for undertaking the works to a very high standard, being very cooperative and nicely fussy on the end result.

The following images show the impressive result obtained from the tamp, we just wish our whole track was up to this standard now, but if we keep going at the rate we are, that may not be many years away.

img20200708093041img20200708093101img20200708093127img20200708093134img20200708093138

Hopefully the pictures show the quality improvement when compared to the earlier shots during the re-sleepering works. The last pic clearly shows the removal of the catch-points, which was really on our wish-list of things to do during the shutdown, however we successfully achieved everything on our list and more!

img20200713125645

More recently we’ve turned our attention back to the Carriage Shed at Castlemaine, with 3 siding now ballasted with a nice gravelly medium ready for jacking to the correct height and tamping, this should leave a nice even walk-able surface in the shed for foot traffic.

img20200713131637img20200713154642

The ring around the turntable also required a kerbing as part of the site permits, to help prevent accidentally driving into the hole. This has now been finalised, with 2nd hand timber sleepers fastened into the ground with hidden steel rods (no sharp edges or tripping hazards) and reflective tape affixed for extra assistance at night.

The setting out of the trackwork for the other side of the turntable and into the shed has begun, with a layout plan of works expected shortly. Things at Castlemaine are really starting to come together, with most items now in or close to their eventual homes and almost all the services now fully connected and functional.

There is a lot to go yet, a lot of planning, organising and doing to be get the job done. The most challenging part for the civil gang is going to be to be fitting in all the various projects we have on the go over the next 2 years, all while maintaining and improving our running track.

But we’ve proven over the past few years and especially during these Covid-19 times that we can undertake an enormous amount of work when we set our minds to it. But we can always use extra hands and it’s looking like it’ll still be some time before trains are back running as usual. We’ve got a good window of trackwork ahead so we plan on making good use of it. Please contact Will via ganger@vgr.com.au if you’re interested in helping out and for details of how we’re managing the risk of Covid-19 on our workdays.

We’ll be at Castlemaine this week (Thurs and Fri) sorting some fastenings that are surplus to V/Line follow their recent works (but valuable to us), meeting Carriage Shed Castlemaine from 8.15am or on site along Kennedy Street from 8.30am.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s