Rail Preparation

With two full gangs (Thurs and Fri) predicted for later this week and good weather we’ll be re-railing a section of Tangent 15-16.

So we spent today busily preparing for it. Sleeper plates and dog spikes were distributed, where needed and brought up from Muckleford.

The main part of today was preparing enough rails to do the work, of which we managed to prepare more than needed.

It should be a great couple of days out on the track gang!