As promised more pics of our latest contract job in Bendigo. Today was very successful, with the job now ready to put together next week.
The excavation for the new track and turnout.
New sleepers to support the remaining track layed through the concrete.
A shot of the works at close of play today, sleepers are in place for the south end of the new road, and rails are positioned alongside ready to be moved over next week.
In the north section of the job the trench through the existing concrete slab has been dug and rubble removed, we’re expecting crushed rock for the road bed to be delivered Monday and that portion will be tackled next.
We’re at Bendigo all next week and we can always use a hand, please contact Will at ganger@vgr.com.au if you’re interested.