80lb Rail

We’ve been busy preparing more 80lb per yard rail to go into our running line.

The rails required cutting when they were transported to the railway from Bandiana.

As a result we either need to drill holes or cut off an old weld at one end of the rail before we can use them.

The pic above shows us laying the rails out for drilling or cutting.

The rails are then loaded onto our well wagons for transport to site.

We ran out around 60 rails to various places along the railway this week, the pic below shows us shunting our train back into Muckleford yard after completion.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s