Job Done!!

What has been the best part of 12 months in the making is now complete! 4.2kms of continuous concrete sleepers between Maldon and Pipeline Crossing.

A few hundred metres of this were completed over the past few years, but the vast bulk of the job was this year.

It’s been a long and at times tedious job, however it’s a massive step towards getting us to a standard which we can realistically maintain. There’s still a long way to go, lots of ballast, tamping and drainage works to ensure years of a minimal maintenance Railway, but the bones are now in place to allow that to happen.

Thursday’s crew had the job of clipping up well in hand, with the final clips pulled on well before morning tea.

Once the clipping up was completed, it was onto the task of jacking and packing. It’s not a lot of fun, however the most amazing part of this process has been just how little jacking has been needed to achieve a relatively smooth top – something it most definitely didn’t have previously.

We continued the jacking and packing process right back along the straight as required. It’s likely we’ll continue to need to do this at regular intervals until we can acquire sufficient ballast and get a proper tamping pass over the length – however this is a small trade off by comparison to keeping the rotten timber sleeper sections in a safe condition.

The last job on Thursday was to remove the temporary 15mph speed restriction and return it to the now permant limit of 20mph for this section (once ballasted and tamped we’ll be in a position to raise it to 25mph in line with our maximum speed, however that’ll be some years away we expect).

A selection of pics, all at different locations along the same straight length, showing how much of a significant portion this straight has been in the overall Maldon to Pipeline Crossing project.

We’re pretty proud of our efforts here. It’s not perfect, but the heavy lifting is now behind us on the path to make it perfect.

Friday’s crew got the exciting job of bundling and strapping the timber sleepers, we actually had a pretty respectable recovery rate from the last little section we completed, the section down towards the tip crossing was very poor with an awful recovery rate.

A bit of a ballast shoulder (if you can call it that…) was pulled up right the way to Pipeline crossing, just to aid in holding it there in the heat, however, given the struggles we have trying to line it once it’s fully clipped up, we suspect this movement will be minimal – certainly no early signs – one advantage of short rail lengths.

Friday was a relatively early finish on site, which gave us time to tidy up and sort out some of our chaos at Maldon, including some grass cutting. Both trucks needed months’ worth of tools and consumables packing away and sorting. We barely recognise the back of the gang truck now! It turns out there was actually a floor under all that mess.

In unrelated matters, during the recent repainting works being undertaken around Maldon station, the platform lamps have been stripped back and repainted, that fresh shiny paint really makes these features ‘pop’.

It’s been a very busy year and we’re pretty much done now, we’ll have a small skeleton crew on hand on Tuesday to tend to a few small tasks but basically we’re in fix it mode now, trying to get on top of a few issue that have developed across the machinery fleet, ready to do it all again next year!

Hopefully, late next week, we’ll have had time to collate this year’s stat’s into a meaningful and highly riveting table to highlight just how much work we really did achieve this past 12 months!

Thankyou to everyone for all your contributions this year – it’s been one hell of a team effort!

Sleepers

Today was very momentus, we’ve now installed all the concrete sleepers requires you 100% concrete sleepers Maldon to Pipeline Crossing.

It’s a long way that we’ve resleepered this year – 4200m, which is over half way to Muckleford and 1/4 of our overall track length! It’s been a massive year.

They’re in, the hardest, most labour intensive, the most time and resource consuming part of the resleepering work for this section is now behind us!

We set out to resleeper from the curve pictured above to Pipeline Crossing this year… and we’ve well and truly exceeded that ambitious target. It’s been a slog. However, the work we’ve put in this year will have dividends for decades. The job is far from over, we still need to complete through to Castlemaine (although that seems far more realistic and much less daunting now), we still need to obtain and distribute many many thousands of tonnes of ballast and get in a production tamping crew to get the track up to a standard that will be sustainable for our limited resources.

We’ll do a piece closer to the end of the year with the details of our plans for next year, however they focus very heavily of resleepering Pipeline Crossing to Muckleford Yard, a distance of 3200m, which based on this year’s experience we should be comfortably able to achieve. Funding the work will however remain a struggle – please reach out if you’re able to help.

We’re actually not quite as ‘done’ with today’s little task as the above may read, approximately 40 sleepers still need their final clips pulled, we’ve got a mountain of clean-up to do and we need to run through from Curve 21 to Curve 20 fixing a few geometry issues we didn’t get to during the resleepering – all should be achieved this week however if we can get enough people on the ground on Thursday and Friday.

Thursday’s gang will meet at Maldon at 8am.

Sleepers

We’re on the home straight now. Advantage of a train free Monday was made good use of today, with the 1 in 4 pattern inserted and partly clipped up right through to Curve 20.

We should comfortably get 1 in 2 clipped up tomorrow and the rest inserted, we may even get a good few of those clipped up to.

Meeting at Maldon at 8am tomorrow or on site from 8.15am

More sleepers

Well, it turns out that declaring yesterday hot was an understatement… today eclipsed that – probably not temperature wise but certainly in regards to humidity and lack of wind. It was horrid.

However we did get the remaining 80 sleepers inserted and clipped up as well as fixing a ramp at the UP end for trains this weekend.

That’s all that’s left to go now, until we can proudly say that 1/4 of our railway is 100% concrete sleepered. It’s roughly 170 sleepers, pretty much the same as this week in the adverse conditions.

We should comfortably knock it over next week, as the temperature is far more attractive at mid 20s.

Tuesday’s crew will meet at Maldon at 8am, then out on site shortly after.