Concrete Sleepers

Things are progressing well out on the resleepering works, with the first pass of the intermediate sleepers inserted and clipped up today, instead of having the gang watch the remainder being inserted we diverted to distributing more sleepers to allow works to progress.

Many hours were spent sorting, preparing and dropping out fastclip sleepers, in fact the whole stockpile in this pic has been distributed, allowing another good few hundred sleepers to be installed over the coming weeks.

Tomorrow’s crew will meet at Maldon at 8am or out on site from 8.30am to continue with the preparations and distribution – it’s never a fun job but a necessary evil in the process.

Often requested has been a progress map of our work on the track, it becomes a very complex task as there is many facets to our works and where does one draw the line as to current works and previous efforts. As part of our record keeping process we do plot our works on a map and we’ve attempted to make that a little more available and accessible – it’s a very large PDF which will require zooming in to see, however hopefully it’ll be of some value – it may be best viewed on a computer.

We’ll endeavour to update this monthly while the major works are occurring.

Progress as of March 2025:

Concrete

Another successful start to the week, with 26 sleepers in and clipped up in the 1 in 4 pattern – it could have been more easily, however for now, that’s all the sleepers we have distributed.

Tomorrow’s crew only has 78 to get under and clip up, then we can get onto distributing the next 1800 sleepers towards Donkey Farm Trk!

Tomorrow’s crew will meet Maldon 8am or on site from 8.30am.

Concrete and tamping

Today was all about finishing off the section of concretes we’ve been working on this week – a total of 144 were installed this week, not a record, but still a solid start given we’re easing back into it.

Lots of jacking and packing to tidy up a few dips – most of which were there well before we installed the concretes – this process is improving our overall geometry quite significantly.

A little bit of preparation work was undertaken for next week, however once we’d knocked over the concrete sleepers, it was onto other things.

We corrected a few notable geometry issues out between Muckleford and Castlemaine, nothing major but much easy to attend to them before they worsen.

The approaches to Rifle Range had settled a little, this was a nice easy fix.

A small amount of settlement had occurred near Walmer Road Crossing, nothing too exciting, but while we had the tamper on, it was an obvious one to tend to.

At the end of another week we’re edging ever closer to Muckleford on our quest to replace the very aged timber sleepers, we’re getting there.

Next week will be a carbon copy of this week, except we’ll be working a little further down the track, hopefully getting well into the curve. Meeting at Maldon at 8am on Monday, on site from 8.30am.

Concrete Sleepers

The last 2 days have been quite productive, with around  56 concrete sleepers now under and clipped up beyond the crossing, with around 125 still to be installed.

Unfortunately for reasons that we can’t remember, when we rerailed through here many years ago, we set the joints at odd locations, meaning using concrete sleepers was near impossible as fishplates were in the way, so we’ve reset the joint stagger to a half rail length to overcome this issue.

It ended up being a very easy process, much easier than we anticipated, meaning we were able to spend the afternoon working on even more resleepering.

It’s a little hard to see, however a keen eye will note that we’re not too far off the curve now. All being well we’ll have most of the sleepers under and clipped up tomorrow. 

We’ll be meeting on site from 8am, no need to head to Maldon first.