Concrete Sleepers

80 concrete sleepers were distributed today in preparation for re-sleepering near Midland Hwy on Thursday.

The sleepers were placed, 4 at a time, onto the running line (can be just seen at the left) before being run across the crossing and out to the required locations.

The pink marks in the centre indicate sleepers that are to be replaced on Thursday, we’ll be working on this curve and the short straight towards MacLise St.

It should be a very interesting day, undertaking the concrete sleeper renewals with the full gang for the first time – no doubt lots will be learnt. Hopefully we find that our 80 is well within a days work!

Please feel free to come along and help out, we’ll be on site from 8.45 on Thursday.

3 thoughts on “Concrete Sleepers

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s