A new week and well refreshed crew resulted in a very productive Monday.

After today’s effort we have fastened down both straight rails in the turnout, which required cutting to appropriate lengths and lining to ensure they were perfectly straight.

Here Bazz and Ian are cutting and drilling rail.

Drilling some more holes before bolting up the rails and fastening them down.

The team tidying up after a long days work, very proud of their efforts.

Back at the other end of the job and concrete pouring has begun, this should be completed and well on the way to curing once we’ve completed the turnout.

We’ll be on site all this week, still plenty of time to help out!.