Today saw us achieve a bit more than we expected, with the high leg of Curve 13 now fully rerailed and clipped up.
We had actually done most of the hard work already for this, with all the timber sleepers adapted to take pandrol clips, so it was just a big day of unclip then re-clip.
It’s come up looking very smart, also releasing a good number of fishplates for our other re-railing.
Today’s crew of 9, very comfortably knocked over this task of re-railing 190m, finding time to clean up and sort all the jewellery and even stack more sleeper plates onto pallets!!
Our bolt delivery has now arrived, meaning we can get back into normal rerailing on Thursday. Meeting Maldon 8am out by Boundary Track from 8.30am
Today was certainly a mix bag. Beginning, we installed the closure that we didn’t quite get around to yesterday.
Then we moved onto the task of marking up the failed timber sleepers (of which we have been quite ruthless, as we really don’t want to back here within the next 5 years) we’ve marked up 120 so far and that’s only to where we’ve rerailed both legs.
We’ve begun dropping out sleeper plates, however, only around a pallets worth, which got us a few hundred metres up one leg. Then, off to Muckleford to pull more plates out of the stack and onto pallets.
Now we know it’s generally the Tuesday gang that revel in this particular task, so we made sure we left enough plates unstacked for Tuesday’s crew, as we’d hate for them to miss out.
However, in the afternoon, between rain showers, we set about getting ready a short section of track that we’re going to re-re-rail (that’s not a typo).
Many years ago, the high leg of this curve was rerailed in 80lb. However, we’ve since rerailed everything else around it in 94lb, leaving just the few hundred metres of the high leg of this curve as 80lb, so to correct that, we’d always planned on swapping over to 94lb.
We’re running a little short on fishplates for the current rerailing, so by doing this swap over next week, with the longer 94lb rails, we’ll get a good number to allow us to proceed out past Boundary Track. It does feel a bit like robbing Peter to pay Paul, but it’s a job we were always going to do sometime. This just brings it forward a year or so.
We may also end up re-rerailing a few other sections towards Maldon in the coming months for the same reason, however they’ll focus very much on areas that would benefit long term from this treatment.
Tuesday’s crew will hopefully knock this over. If not, then at least make a good start. Meeting at Maldon at 8am or on site (Muckleford) from 8.30am.
Today was certainly a mix bag. Beginning, we installed the closure that we didn’t quite get around to yesterday.
Then we moved onto the task of marking up the failed timber sleepers (of which we have been quite ruthless, as we really don’t want to back here within the next 5 years) we’ve marked up 120 so far and that’s only to where we’ve rerailed both legs.
We’ve begun dropping out sleeper plates, however, only around a pallets worth, which got us a few hundred metres up one leg. Then, off to Muckleford to pull more plates out of the stack and onto pallets.
Now we know it’s generally the Tuesday gang that revel in this particular task, so we made sure we left enough plates unstacked for Tuesday’s crew, as we’d hate for them to miss out.
However, in the afternoon, between rain showers, we set about getting ready a short section of track that we’re going to re-re-rail (that’s not a typo).
Many years ago, the high leg of this curve was rerailed in 80lb. However, we’ve since rerailed everything else around it in 94lb, leaving just the few hundred metres of the high leg of this curve as 80lb, so to correct that, we’d always planned on swapping over to 94lb.
We’re running a little short on fishplates for the current rerailing, so by doing this swap over next week, with the longer 94lb rails, we’ll get a good number to allow us to proceed out past Boundary Track. It does feel a bit like robbing Peter to pay Paul, but it’s a job we were always going to do sometime. This just brings it forward a year or so.
We may also end up re-rerailing a few other sections towards Maldon in the coming months for the same reason, however they’ll focus very much on areas that would benefit long term from this treatment.
Tuesday’s crew will hopefully knock this over. If not, then at least make a good start. Meeting at Maldon at 8am or on site (Muckleford) from 8.30am.
Today saw us insert a staggering 520m of 80lb rail, a total of 13 x 40m lengths.
Unfortunately, we did manage to get quite soaked in this morning’s rain, even having to sit out about an hour until things settled down.
However just after morning tea, the skies dried up and we got to work.
We’ve certainly got nicely back into the swing of rerailing, all day the clipping up crew were hot on the heels of the digger swapping over the rail.
We didn’t need to cut any rails today, we just had to move two sleepers very slightly, to work with the joints.
By day’s end, we were well over 2/3rds of the way towards Boundary Track along this leg. Only around 8 lengths to go. However, as we’ve greatly over-achieved today, we haven’t got our delivery of track bolts yet, so we’ll have to hold off getting any more rail in until they arrive next week.
However, tomorrow’s crew has still got plenty to do, the closure back to 60lb still needs to go in, we can begin the exciting task of dropping out sleeper plates as well as beginning to prepare the next section for rerailing.