Some pictures

While we’re still waiting to get an idea on the time before we can get a digger back, here are a few pictures from it in action last Friday.

Changing sleepers and unloading more sleepers at Boundary Trk, ready for the next section that requires renewals (Boundary trk to Rifle Range Bridge).

We managed an impressive 63 sleepers on Friday, which completed that section, a total of 166 for the length between the crossings. We’ve likely still got another 200 to replace from Boundary Trk down to Brown Street.

Short of a bit of tamping and a bit of ballast tidying, we can just about call this short section complete, meaning it’ll soon be time to begin on section towards Rifle Range Bridge, all being well that’ll be next week.

However, as for the next few days, we’ll be focusing on odd jobs around Maldon Yard, we’ve got a few bolts to tighten, a good amount of signalling gear to lubricate and no doubt we’ll keep busy. Meeting at Maldon from 8am

Digger

Yep, well the digger is certainly broken, we think we’ve narrowed it down to the slew pinion, unfortunately inspecting it proved to be impossible without removing the slew motor, it’s now loose and tomorrow will involve the removal and inspection.

Despite not having a formal workday, a lot was still achieved, with various odd jobs, including mowing some of the overgrowth, poisoning some weeds, collecting gluts, replacing a trolley wheel and generally assisting with the digger.

At this stage we’re extremely unlikely to have the digger back in action this week, so we’ll still have workdays, but they’ll focus very much on odd jobs around Maldon Yard, meeting there from 8am on Thursday.

Digger Broke

Well, after such a great day on Friday, where we did complete all the sleepers between Sawmill Rd and Boundary Trk, today while moving Concrete sleepers, the slew on the big digger decided it had done enough slewing and promptly gave up!!

Hopefully it’ll be an easy fix, but it is likely to take all day tomorrow, so we won’t have a formal workday, but if anyone would still like to enjoy Sunny Maldon, we’ll be there from 7.30am and could no doubt use an extra pair of hands pulling apart and reassembling.

Sleepers

To say that resleepeeing today was a success might be a little of an overstatement, as upon installing the 15th sleeper of the day… the ram that connects the two halves of the grabs fell off.

In reality, it ended up being very fixable, as it had just cracked around the weld and a simple trip to Castlemaine to pull the ram out of the grabs and re-weld the nuckle to the ram was only a few hours inconvenience.

It’s quite remarkable that the weld hadn’t let go sooner, as it had some evidence of an aged crack once on the workbench, not that you would ever have detected it when still on the grabs.

Anyhow, after deciding to double the amount of weld, compared to the factory amount (which was actually probably quite sufficient, likely just a minor welding defect when constructed) and a good solid test, it’s now as good as new! The one thing that really impressed us was the ease with which we were able to pull the grabs apart and reassemble, very happy with that feature.

Given what we’ve put these grabs through, we could hardly complain, they’ve done some amazingly hard tasks.

Once the excitement and heroic effort of the workshop staff got us out of trouble – thanks Bazz and Harry, we returned to site to get another 31 sleepers installed, taking us up to 45 for the day, had we not lost 3.5hrs to this, we’d probably have completed from Boundary Trk to Sawmill Rd.

We’ll have a red hot crack at doing that tomorrow however. We will be meeting at Boundary Trk from 8.30am, however, we’re really closer to Sawmill Rd now, so if you arrive much after 8.45am, it’s probably best to head straight to Sawmill Rd and walk up.