Well, after a big effort, we’ve now completed the installing component of our resleepering program for 2026.

As with the last section of fastclips we did, we’re yet to come back and clip ever single sleeper up, however the hard yards are complete and once the bits are on hand it’s only a day or two to knock that over.




Today was all about tidying up and getting the gear back home.



We’ve bundled up all the loose sleepers and loaded them onto a wagon at Muckleford.


We even recovered a concrete sleeper that found its way a little too far down the embankment!

Next week will be a maintenance week primarily, centred around Maldon, meeting there each day from 8am. The roses at Maldon are looking very impressive. Well, worth a look if you’re passing by.