Concrete Sleepers

Last week ended up being very successful  will 200 concrete sleepers installed, leaving only about 140 to go to get to the Bridge.

We built on the success of earlier in the week, which all went very smoothly.

We had a minor hose issue on the digger. However, these repairs take only minutes now, so it wasn’t a major impact.

Very little to go until we reach the bridge now.

The usual activities of clipping, jacking and packing, giving a result at least as good as it was before we started.

All tidied up and timber bundled, it was a very neat result for the week.

There will be no workdays on Monday or Tuesday this week (due to the cup), however, business as usual on Wednesday and Thursday.