Concretes

Sorry about the lack of updates this past week, it’s been busy!

The week was highly successful with another 150 concretes installed, this took us all the way to the start of the curve.

It’s very hard to tell in these pics, but we have now been through all the stacks of sleepers in the area and dropped out towards the Bridge, ready to continue on.

We had a test run of T395/Y157 pass through the worksite on Thursday, which we piggy backed onto to make a civil transfer.

The next couple of weeks will be a bit quieter, as we’ve got quite a few away, however we do have a large number of bonfires that will need tackling prior to the fire season beginning so we’ll be getting onto those.

Tomorrow’s crew will meet at Maldon at 8am.