Well, we’ve finally made it to Donkey Farm Track, almost – just the infill sleepers to go, and we’ll be there.



It was a pretty regular day, nothing too out if the ordinary.


Once the final few sleepers go in later this week, we will have installed around 2000 concrete sleepers between Pipeline and Donkey Farm Track crossings since March – not a bad effort at all.


Tomorrow’s crew will be meeting at Maldon at 8am or on site from 8.30am, finishing off and bundling timber sleepers.