Concrete Sleepers

We had a very successful day today, inserting and clipping up 107 additional concrete sleepers in Curve 16. This take us to just outside the cutting – which we’re extremely happy about, this isn’t by any stretch the worst cutting, however they are always extremely awkward places to work in.

As yet, it hasn’t received its final tweaking, however its looking amazingly good already. Another 50 or so have been prepared ready to be tackled this week, with tomorrow’s crew set to start that out on site from 8.30am (meeting Maldon 8am).