Today we completed the last of our little rerailing effort for now, 71m of rail installed into each leg.

It all happened with great ease, in the same basic style as Yesterday’s work, even having enough time to give it all a tamp and tidy up as well as break up most of the old 80lb rail removed – this rail would be fine for a low to no use siding or as rail to make stuff (such as low retaining walls or sleeper cradles etc…) so we’ll finish off breaking this up on Tuesday before we load it up onto a wagon for storage down at Muckleford.
Tuesday’s crew meeting Castlemaine Depot from 8am