After having so much fun destructing things last week, we were champing at the bit to do some more today.
![](https://vgrcivil.blog/wp-content/uploads/2024/06/20240624_0957383751496520055099375.jpg?w=768)
Today’s victim was the old trolley road / oil store turnout at Maldon, it’s time was also up.
We managed to take an extremely small number of pictures of the interesting bits, however it was a real hodge podge of tierods, steel sleepers, rotten timber sleepers and some very corroded rail.
![](https://vgrcivil.blog/wp-content/uploads/2024/06/20240624_1542225523378020944983214.jpg?w=768)
And like magic.. the concrete sleepers and replacement rails are in!
This is somewhat of a temporary job as it’ll need adjusting quite a bit when the turnout (the one the photo is being taken from) is renewed later this year.
![](https://vgrcivil.blog/wp-content/uploads/2024/06/20240624_1542275743119479361945726.jpg?w=1024)
![](https://vgrcivil.blog/wp-content/uploads/2024/06/20240624_1543442352056579312265297.jpg?w=768)
It certainly changes the appearance of the place however, it actually has a much cleaner look – less cluttered.
![](https://vgrcivil.blog/wp-content/uploads/2024/06/20240621_1407162312415338724925152.jpg?w=768)
![](https://vgrcivil.blog/wp-content/uploads/2024/06/20240621_1407506989783192250853847.jpg?w=768)
These are actually from Fridays efforts, however some slightly improved gate holder openers were installed, these are really high tech, using a snap hook to connect a chain to the gate, preventing it blowing open. Given that when we arrived today the D shackles had been undone and chains unthreaded, we highly suggest if you’re not certain of how snap hooks work – please save these pictures to your phone as a future reference and or google ‘Snap Hooks’.
Tomorrow’s crew will be meeting at Maldon from 8am, where we’ll assemble the track bits and pieces laid out today.