Sleepers

Another very successful one today, with the 1 in 2 inserted and clipped up down to Pipeline Crossing. A very impressive effort for our small team of 4.

A big machinery day tomorrow and we should have most of the concretes under and all the timber tidied up ready for a big clipping up day on Thursday.

There won’t be a workday tomorrow on account of the volume of machine only work required, however Thursday’s workday will go ahead as planned, meeting at Maldon 8am or on site from 8.15am.