Were churning through Curve 17 at a great rate, with around 160 sleepers installed and clipped up today, leaving around 80 to insert on Thursday.


It’s a very well-oiled machine now, achieving very significant numbers, we can almost see Pipeline Crossing from where our end point will be this week.

There won’t be any workday tomorrow, however we’ll be back into things as normal on Thursday, meeting Maldon 8am or on site from 8.15am.