Just one pic today, the 2nd pass of sleepers are now inserted and clipped up, leaving tomorrow as an action-packed day of inserting the remainder.
There won’t be a formal workday tomorrow, as it will be a day of excavator work to get the sleepers under and tidy up the timber sleepers etc etc…
Thursday however will be all systems go from 8.15am on site (8am at Maldon) to get everything clipped up. If all that goes to plan, we’ll likely do an extra 50 or so sleepers on Thursday Afternoon.