We had another good crack at inserting concrete sleepers today, with another 32 installed, we had a few other tasks to tend to as well today, so not quite as productive as on Thursday.


We’re actually very happy with how little effort is needed to get the track to a quite comfortable smoothness following the concrete sleepering, its much better than we expected.
We’ve now got a 60m ish stretch of full depths in the track, only many kilometres to go now!
We’ll be back into out here on Thursday and Friday, when we’ll hopefully get at least 150 in over the two days, quite possibly a few more however as we’re now learning quite a bit about what to do and how to go about it. Meeting at Maldon at 7.45am or on site (old tip crossing) from 8am