Friday proved to be an extremely successful day, with the whole UP leg drilled and spiked, between Sawmill Rd and Boundary Track, quite a phenomenal effort for our gang of 4.

Today saw us distributing more of the concrete sleepers that are currently arriving at a rate of one truck load a week, we’ve focused on getting them out around Bendigo Road crossing, where it’s hard to unload a train due to the track circuiting.

So far 440 have arrived and been dropped out trackside, with hopefully another 3600 still to come!

Tomorrow’s workday will be installing concrete sleepers between Boundary Trk and Sawmill Rd, meeting Maldon 8am or Boundary Track from 8.30am.